Follow Measure first: sensors read voltage at substations, capacitor banks, and end-of-line locations along the feeder. Optimize uses these readings to choose a safe voltage reduction that saves energy without affecting equipment. Actuate then changes transformer tap settings and capacitor switching in real time to apply that setting. Capacitor banks manage reactive power, shown as VARs, to help support voltage along the feeder. Result shows 2–4% energy savings across the distribution system while power quality remains acceptable. Finally, Verify the Result checks the conservation voltage reduction (CVR) example: 120 V becomes 116 V. The calculation gives a 3.3% voltage reduction, and the figure places 116 V within ANSI standards. For resistive loads, the stated 2–4% energy savings can occur without affecting performance.