Testing a Missing Vendor Interface

Testing a Missing Vendor Interface

Try Tap Step to reveal the Vendor E delivery timeline and compare the estimated and actual weeks for energy integration.

Testing a Missing Vendor Interface

Step-through animation

Case record

The other building systems depended on Vendor E's energy interface, which was missing when the team needed it.

Observe The schedule reveals 4 estimated weeks and 16 actual weeks. Later, the exchange diagram moves from an expected numeric reply with the mock to a different representation and a failed assertion with the real adapter.
Explain In frame 5 the numeric assertion fails because the vendor sends the reading in a different representation and the adapter passes it through unchanged. The mock had supplied the numeric reply required by the contract.

Technical boundaries. The opening schedule belongs to the case record. The contract, mock and adapter sequence is shown as proposed prevention, with symbolic version labels. The final panel gives conditional release evidence based on compatibility and end-to-end commissioning, with both retest outcomes left open.