Testing a Missing Vendor Interface
Testing a Missing Vendor Interface
Testing a Missing Vendor Interface
Step-through animation- Building-side contract version
- Agreed (symbolic)
- Vendor API version
- Awaiting verification
Vendor API delivery
- Promised
- Q4
- Arrived
- Q2 next year
Energy integration
- Estimated
- 4 weeks
- Actual
- 16 weeks
- Gap
- 12 weeks
Interface contract
Define the requests the other building systems can make and the replies and errors they expect.
Release evidence pending.
Building-side mock checks passed
Real compatibility pending. Release evidence pending.
Real compatibility failed
The vendor returns an energy reading in a different representation. The adapter passes it through unchanged, so the assertion expecting a numeric reading fails.
Mock checks passed. Commissioning pending. Release evidence pending.
Plan reopened
Reserve explicit integration margin. Set its duration in the project plan.
- Vendor delays
- Protocol mismatches
- Commissioning checks
Adapter correction ready for retest. Release evidence pending.
Proposed retest
- Rerun real compatibility against the pinned building-side contract and verified vendor API.
- Run an end-to-end commissioning check with the real systems.
- Both checks pass
- Record both versions and both results as release evidence.
- Either check fails
- Keep release evidence pending and return to the reopened plan.
The other building systems depended on Vendor E's energy interface, which was missing when the team needed it.
Technical boundaries. The opening schedule belongs to the case record. The contract, mock and adapter sequence is shown as proposed prevention, with symbolic version labels. The final panel gives conditional release evidence based on compatibility and end-to-end commissioning, with both retest outcomes left open.